Finance: Revenue Assurance β Reconciliation
What this page is for
Reconciliation is the month-end close: for any range, it checks what was produced against what was submitted, what the utility accepted, what was invoiced and what was collected, per project, state, utility or aggregator. Open it to confirm each project reconciles within tolerance, and to see where the money stopped.
Find it under Finance β Revenue Assurance β Reconciliation. It has two views: Summary (the default) walks the range as two waterfalls; Table shows the match per row.
The toolbar
Control | What it does |
|---|---|
β Project | Limits the page to one project, a state, or any set of projects. |
Filter (funnel icon) | Shows a second row of chips: Type , State , Utility , Aggregator and Flag . Each chip opens a checklist with a count per value. |
Search project, state, utility... | Finds rows by name. The counter shows how many projects match. |
Period | Monthly, Quarterly, Annually or Life Time, with arrows to step back and forward. |
Summary / Table | Switches between the two waterfalls and the table. |
Upload Data | Opens Data Feeds. |
The KPI strip
Figure | What it shows |
|---|---|
Produced | Metered generation over the projects and months in view, with the planned figure from your generation model and the utility meter against your DAS on complete DAS months. |
Submitted | kWh the aggregator asked the utility to credit, as a share of produced (on months with allocation data). |
Accepted | kWh the utility credited and kept on subscriber bills. The rest was returned or rejected, each kWh with an account and a reason. |
Recoverable loss | Credits returned to the host bank or rejected, in dollars. |
In-flight | Credits accepted but not yet on a bill, from the three newest months. Timing, never loss. |
Invoiced β collected | The utility's own legs: sponsor payment due on its applied-credit reports, against what its payment reports show as paid, on the same bill periods. The aggregator's figures sit underneath. |
Max revenue β collected | The maximum revenue the credit could bring (total credit on the host bills, net of the subscriber discount and the utility's admin fee) against what was collected, on the bill periods with a payment report. Amber from 2%, red from 5%. |
Hover the β on the two money figures for the full breakdown.
Summary: the two waterfalls
Each waterfall reads top to bottom. Dark bars are totals; red bars go against you, green ones for you, grey ones are timing or banked credit; a dashed bar is a check that doesn't move the walk. Every line says which document its figure comes from.
Generation Waterfall Β· Expected to Accepted (kWh)
Expected generation (your generation model) β Production vs plan β Utility metered (net injection on the host bills) β Meter check Β· utility β DAS (complete DAS months only) β Retained by host (banked) β Allocated to subscribers β Returned / rejected to host bank β Accepted on subscriber bills.
When a host bill is missing. Each bill period's production comes from the best file loaded for it: the host bill, else the aggregator's report, else your DAS over the bill cycle (complete days only). When every period has a host bill, the bar reads Utility metered. When the sources mix, it reads Metered production, and its line names each source and how many periods it covers, for example "host bills 196 periods Β· aggregator report 30 periods". A period with none of the three is left out, and the line counts it. The meter check uses only the periods with a host bill.
Revenue Waterfall Β· Maximum Revenue to Collected ($)
Expected revenue (when expected rates are provided) β Maximum revenue generated (total credit on the host bills) β Subscriber discount β Utility admin fee β Maximum revenue, net β Banked portion β Allocated portion, net β Applied vs allocated (timing) β Billed / invoiced β Awaiting payment report β Not yet paid β Collected.
The line under the walk gives collected minus maximum revenue (net), like for like on the bill periods that have a payment report.
When a host bill is missing. Maximum revenue and the banked portion come from the host bill. Without one, those lines show a note, Needs the host bill Β· n periods, instead of a number.
- No host bill in the range: the card is titled Revenue Waterfall Β· Allocated Credit to Collected and starts at Allocated credit: the credit transferred to subscribers on the utility's applied-credit report, less the subscriber discount and the utility's admin fee at the shares that report shows. The line under the walk then gives collected minus allocated credit (net).
- Some periods with a bill, some without: the walk runs from maximum revenue on the periods with a bill, and the others join at Allocated portion, net on the line + Periods without a host bill. Billed / invoiced, Awaiting payment report, Not yet paid and Collected cover every period.
- Every host bill in: the walk is exactly as described above.
Table
The tabs By Project, By State, By Utility and By Aggregator set the rows. Export CSV downloads the rows and columns as shown.
Column | Meaning |
|---|---|
Project (or group) | The row, with its type, utility and state. Grouped views add Projects : projects with data out of projects in the group. |
Planned | Expected kWh from your generation model. |
Produced | Metered kWh. |
Meter Ξ | Utility meter minus your DAS, on months with a complete daily DAS record. "no DAS" where none is loaded. |
Submitted / Accepted | As in the KPI strip. |
Invoiced | The utility's sponsor payment due; underneath, the aggregator's figure and the difference on the months both report. |
Collected | The utility's sponsor payment paid; underneath, the aggregator's figure. "aggregator only" where no utility payment report is loaded. |
Variance | The headline variance and its basis (kWh or cash). |
Flag | OK under 2%, Investigate 2-5%, Critical 5% and above. |
How to
Close the month for one project
- Pick the project with β Project and set Period to Monthly.
- In Summary, read the Generation Waterfall: where did kWh drop between metered and accepted?
- Read the Revenue Waterfall: where did dollars drop between maximum revenue and collected?
- For returned credits, open Loss & Root Cause for the account list.
Check the aggregator against the utility
- Switch to Table.
- Read the line under Invoiced and Collected for each project: the aggregator's figure and its difference from the utility's.
- Click By Aggregator to compare aggregators side by side.
Find every project outside tolerance
- Click the filter icon, open Flag and tick Critical and Investigate.
- Switch to Table and sort by Variance.
Reconcile before the host bill arrives
- Upload the utility's applied-credit report on Data Feeds as soon as you have it.
- Open Reconciliation for the period. The Revenue Waterfall starts at Allocated credit and shows Needs the host bill where the bill is needed.
- When the host bill arrives, upload it. The walk then starts from maximum revenue and shows the banked portion.
Send the reconciliation to finance
- Set the period, filters and grouping.
- Switch to Table and click Export CSV.
Notes
- The waterfalls work on bill periods, not calendar months: the utility bills on its own cycle.
- A bill period keeps paying out for two to three months, so the newest periods sit in Awaiting payment report or Not yet paid. That is timing.
- Expected revenue reads "not provided" until expected bill credit rates cover most of the production.
- Applied-credit reports uploaded before 13 November 2026 don't carry the credit total that the Revenue Waterfall uses when a host bill is missing. Upload them again on Data Feeds. The uploader accepts each of those reports one more time.
- The table is wider than most screens. Scroll sideways for Flag and the columns after it.